[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144898":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144898,800,2,"多选题","关于混凝土工程雨期施工的说法，正确的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","对粗、细骨料含水率实时监测，及时调整混凝土配合比",true,{"key":16,"text":17,"correct":14},"B","选用具有防雨水冲刷性能的模板脱模剂",{"key":19,"text":20,"correct":14},"C","雨后应检查地基面的沉降，并应对模板及支架进行检查",{"key":22,"text":23,"correct":24},"D","大雨、暴雨天气不宜进行混凝土露天浇筑",false,{"key":26,"text":27,"correct":24},"E","梁板同时浇筑时应沿主梁方向浇筑","ABC","2020教材P201\u002F 2019教材P203 5.混凝土工程(1)雨期施工期间，对水泥和掺合料应采取防水和防潮措施，并应对粗、细骨料含水率实时监测，及时调整混凝土配合比。(2)应选用具有防雨水冲刷性能的模板脱模剂。(3)雨期施工期间，对混凝土搅拌、运输设备和浇筑作业面应采取防雨措施，并应加强施工机械检查维修及接地接零检测工作。(4)除采用防护措施外，小雨、中雨天气不宜进行混凝土露天浇筑，且不应开始大面积作业面的混凝土露天浇筑；大雨、暴雨天气不应进行混凝土露天浇筑。(5)雨后应检查地基面的沉降，并应对模板及支架进行检查。(6)应采取防止基槽或模板内积水的措施。基槽或模板内和混凝土浇筑分层面出现积水时，应在排水后再浇筑混凝土。(7)混凝土浇筑过程中，对因雨水冲刷致使水泥浆流失严重的部位，应采取补救措施后再继续施工。(8)浇筑板、墙、柱混凝土时，可适当减小坍落度。梁板同时浇筑时应沿次梁方向浇筑，此时如遇雨而停止施工，可将施工缝留在弯矩剪力较小处的次梁和板上，从而保证主梁的整体性。(9)混凝土浇筑完毕后，应及时采取覆盖塑料薄膜等防雨措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]