[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144893":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144893,800,2,"多选题","高温施工混凝土配合比调整的因素有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","环境温度",true,{"key":16,"text":17,"correct":14},"B","湿度",{"key":19,"text":20,"correct":14},"C","风力",{"key":22,"text":23,"correct":24},"D","混凝土初凝时间",false,{"key":26,"text":27,"correct":14},"E","采取的温控措施","ABCE","2020教材P202 \u002F 2019教材P204 3.混凝土工程当日平均气温达到30℃及以上时，应按高温施工要求采取措施。(2)高温施工混凝土配合比设计除应符合规范规定外，尚应符合下列规定：1)应考虑原材料温度、环境温度、混凝土运输方式与时间对混凝土初凝时间、坍落度损失等性能指标的影响，根据环境温度、湿度、风力和采取温控措施的实际情况，对混凝土配合比进行调整；",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]