[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144863":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1144863,800,1,"单选题","关于施工现场动火审批的说法，正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","一级动火作业应编制防火安全技术措施报批",false,{"key":16,"text":17,"correct":14},"B","二级动火作业由项目安全管理部门审查批准",{"key":19,"text":20,"correct":14},"C","三级动火作业由项目责任工程师填写动火申请表",{"key":22,"text":23,"correct":24},"D","动火证当日有效",true,"2020教材P188 \u002F 2019教材P190 三、施工现场动火审批程序(1)一级动火作业由项目负责人组织编制防火安全技术方案，填写动火申请表，报企业安全管理部门审查批准后，方可动火，如钢结构的安装焊接。(2)二级动火作业由项目责任工程师组织拟定防火安全技术措施，填写动火申请表，报项目安全管理部门和项目负责人审查批准后，方可动火。(3)三级动火作业由所在班组填写动火申请表，经项目责任工程师和项目安全管理部门审查批准后，方可动火。(4)动火证当日有效，如动火地点发生变化，则需重新办理动火审批手续。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]