[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144834":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144834,800,2,"多选题","施工现场临时用水量计算包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","现场施工用水量",true,{"key":16,"text":17,"correct":14},"B","施工机械用水量",{"key":19,"text":20,"correct":14},"C","施工现场生活用水量",{"key":22,"text":23,"correct":24},"D","基坑降水计算量",false,{"key":26,"text":27,"correct":14},"E","消防用水量","ABCE","2020教材P176 \u002F 2019教材P178 (1)计算临时用水量。临时用水量包括：现场施工用水量、施工机械用水量、施工现场生活用水量、生活区生活用水量、消防用水量。同时应考虑使用过程中水量的损失。在分别计算了以上各项用水量之后，才能确定总用水量。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]