[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144831":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144831,800,2,"多选题","临时用电组织设计及变更时须涉及到的人包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工现场项目经理",false,{"key":16,"text":17,"correct":18},"B","具有法人资格企业的技术负责人",true,{"key":20,"text":21,"correct":14},"C","建设单位技术负责人",{"key":23,"text":24,"correct":18},"D","电气工程技术人员",{"key":26,"text":27,"correct":18},"E","现场监理","BDE","2020教材P174 \u002F 2019教材P176 (5)临时用电组织设计及变更必须由电气工程技术人员编制，相关部门审核，并经具有法人资格企业的技术负责人批准，现场监理签认后实施。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]