[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144829":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144829,800,2,"多选题","施工现场临时用电工程必须经过验收方可使用，需由()等部门共同验收。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","编制部门",true,{"key":16,"text":17,"correct":14},"B","审核部门",{"key":19,"text":20,"correct":21},"C","合约部门",false,{"key":23,"text":24,"correct":14},"D","批准部门",{"key":26,"text":27,"correct":21},"E","分包单位","ABD","2020教材P174 \u002F 2019教材P176 临时用电工程必须经编制、审核、批准部门和使用单位共同验收，合格后方可投入使用。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]