[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144799":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144799,800,2,"多选题","施工总平面图的设计内容包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建筑物、构筑物位置、平面轮廓",true,{"key":16,"text":17,"correct":14},"B","供水、给水、排水等管线和设施",{"key":19,"text":20,"correct":14},"C","钢筋、木材加工场地",{"key":22,"text":23,"correct":24},"D","幕墙玻璃质量检测室",false,{"key":26,"text":27,"correct":24},"E","装饰装修半成品组装场地","ABC","2020教材P171 \u002F 2019教材P173 施工总平面图的设计内容：(1)项目施工用地范围内的地形状况；(2)全部拟建建（构）筑物和其他基础设施的位置；(3)项目施工用地范围内的加工、运输、存储、供电、供水供热、排水排污设施以及临时施工道路和办公、生活用房；(4)施工现场必备的安全、消防、保卫和环保设施；(5)相邻的地上、地下既有建（构）筑物及相关环境。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]