[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1144738,800,1,"单选题","板材隔墙施工中，支设临时方木紧后工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","放线",false,{"key":16,"text":17,"correct":14},"B","安装隔墙板",{"key":19,"text":20,"correct":21},"C","配置胶粘剂",true,{"key":23,"text":24,"correct":14},"D","安装门窗框","2020教材P145 \u002F 2019教材P144 本题考核的是板材隔墙的施工流程。板材隔墙的施工流程：基层处理→放线→配板、修补→支设临时方木→配置胶粘剂→安装U形卡件或L形卡件（有抗震设计要求时）→安装隔墙板→安装门窗框→设备、电气管线安装→板缝处理。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]