[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144737":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1144737,800,1,"单选题","关于板材隔墙施工工艺流程的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","放线→配板、修补→安装U形卡件或L形卡件→支设临时方木→配置胶粘剂→安装隔墙板→安装门窗框→设备、电气管线安装→板缝处理",false,{"key":16,"text":17,"correct":14},"B","放线→支设临时方木→配置胶粘剂→配板、修补→安装U形卡件或L形卡件→安装隔墙板→安装门窗框→设备、电气管线安装→板缝处理",{"key":19,"text":20,"correct":14},"C","放线→配置胶粘剂一配板、修补→支设临时方木→安装U形卡件或L形卡件→安装隔墙板→安装门窗框→设备、电气管线安装→板缝处理",{"key":22,"text":23,"correct":24},"D","放线→配板、修补→支设临时方木→配置胶粘剂→安装U形卡件或L形卡件→安装隔墙板→安装门窗框→设备、电气管线安装→板缝处理",true,"2020教材P145 \u002F 2019教材P144 板材隔墙施工 （1） 工艺流程基层处理—放线—配板、修补-支设临时方木-配置胶粘剂-安装 U 形卡件或 L 形卡件-安装隔墙板—安装门窗框— 设备、 电气管线安装-板缝处理。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]