[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144724":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144724,800,1,"单选题","关于抹灰工程施工工艺的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采用加强网时，加强网与各基体的搭接宽度不应小于100mm",true,{"key":16,"text":17,"correct":18},"B","灰饼宜用1:5水泥砂浆抹成50mm见方形状",false,{"key":20,"text":21,"correct":18},"C","滴水线应内低外高，滴水槽的宽度和深度均不应小于10mm",{"key":23,"text":24,"correct":18},"D","水泥砂浆抹灰层应在湿润条件下养护，一般应在抹灰48h后进行养护","2020教材P142 \u002F 2019教材P141 非常规抹灰的加强措施：当抹灰总厚度大于或等于 35mm 时，应采取加强措施。不同材料基体交接处表面的抹灰， 应采取防止开裂的加强措施。当采用加强网时， 加强网与各基体的搭接宽度不应小于 100mm加强网应绷紧、钉牢。根据设计图纸要求的抹灰质量以及基层表面平整垂直情况， 吊垂直、套方、找规矩，抹灰饼确定抹灰厚度。灰饼宜用 1 : 3 水泥砂桨抹成 50mm 见方形状。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]