[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144659":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144659,800,1,"单选题","钢筋代换时，其相应费用应征得（ ）同意并办理相应手续。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计单位",true,{"key":16,"text":17,"correct":18},"B","监理单位",false,{"key":20,"text":21,"correct":18},"C","总包单位",{"key":23,"text":24,"correct":18},"D","建设单位","2020教材P107 \u002F 2019教材P106 本题考查的是钢筋工程。钢筋代换时应征得设计单位的同意，并办理设计变更手续。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]