[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144657,800,1,"单选题","防水混凝土留设有后浇带时，当设计无要求时，至少应在原混凝土浇筑完成后（ ）d才能进行后浇带混凝土浇筑。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","21",false,{"key":16,"text":17,"correct":18},"B","28",true,{"key":20,"text":21,"correct":14},"C","14",{"key":23,"text":24,"correct":14},"D","60","2020教材P112 \u002F 2019教材P111 后浇带是在现浇钢筋混凝土结构施工过程中，为克服由于温度、收缩等原因导致有害 裂缝而设置的临时施工缝。后浇带通常根据设计要求留设，并在主体结构保留一段时间 （若设计无要求，则至少保留28d）后再浇筑，将结构连成整体。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]