[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144655,800,1,"单选题","关于后张法预应力（无粘结）施工的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预应力混凝土楼盖中的张拉顺序是先张拉楼面梁、后张拉楼板",false,{"key":16,"text":17,"correct":18},"B","无粘结预应力筋长度不大于40m时，可一端张拉，大于40m时，宜两端张拉",true,{"key":20,"text":21,"correct":14},"C","当曲线无粘结预应力筋长度超过20m时，宜采用两端张拉",{"key":23,"text":24,"correct":14},"D","当长度超过30m时，宜采用分段张拉","2020教材P113 \u002F 2019教材P112 （5） 预应力张拉要符合设计要求；通常预应力筋张拉方式有一端张拉和两端张拉； 有粘结预应力筋长度不大于 20m时，可一端张拉，大于 20m 时，宜两端张拉； 预应力筋 为直线时，一端张拉长度可延长至35m，无粘结预应力筋长度不大于40m时，可一端张拉， 大于40m时，宜两端张拉。 预应力楼盖宜先张拉楼板、次梁，后张拉主梁的预应力筋；对于平卧重 叠构件，宜先上后下逐层张拉。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]