[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144646":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144646,800,2,"多选题","预制构件存放要求正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多层叠放时，每层构件间的垫块应上下对齐",true,{"key":16,"text":17,"correct":18},"B","预制楼板、叠合板构件宜立放",false,{"key":20,"text":21,"correct":14},"C","阳台板、空调板构件宜平放",{"key":23,"text":24,"correct":14},"D","预制内外墙板宜立放",{"key":26,"text":27,"correct":18},"E","叠放层数不宜超过5层","ACD","2020教材P128 \u002F 2019教材P127 3.存放要求（ 1 ） 存放场地应平整坚实，并有排水措施；（ 2 ） 存放库区已实行分区管理和信息化台账管理；（3） 应按产品品种、规格型号、检验状态分类存放，产品标识应明确耐久，预埋吊件朝上，标示向外；（4） 合理设置支点位置，并宜与起吊点位置一致；（ 5 ） 与清水混凝土面接触的垫块采取防污染措施；（6） 预制构件多层叠放时，每层构件间的垫块应上下对齐；预制楼板、叠合板、阳台板和空调板等构件宜平放，叠放层数不宜超过6 层；（7） 预制柱、梁等细长构件应平放，且用两条垫木支撑；（8） 预制内外墙板、挂板宜采用专用支架直立存放，构件薄弱部位和门窗洞口应采取防止变形开裂的临时加固措施。答案选ACD。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]