[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1144643,800,1,"单选题","压型钢板与其他相关联的工序流程中，堵头板和封边板安装紧后工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","压型钢板安装焊接",false,{"key":16,"text":17,"correct":14},"B","清扫、施工批交验",{"key":19,"text":20,"correct":14},"C","栓钉焊",{"key":22,"text":23,"correct":24},"D","压型板锁口",true,"2020教材P126 \u002F 2019教材P126 压型钢板与其他相关联的工序应按下列工序流程进行施工：钢结构隐蔽验收→搭设支顶架→压型钢板安装焊接→堵头板和封边板安装→压型板锁口→栓钉焊→清扫、施工批交验→设备管道、电器线路施工、钢筋绑扎→混凝土浇筑。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]