[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144582,800,1,"单选题","施工期间最高气温超过30℃时，现场拌制砂浆使用完毕时间是（ ）h内。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2.0",true,{"key":16,"text":17,"correct":18},"B","2.5",false,{"key":20,"text":21,"correct":18},"C","3.0",{"key":23,"text":24,"correct":18},"D","4.0","2020教材P115 \u002F 2019教材P114 三）砂浆的拌制及使用 （3）现场拌制的砂浆应随拌随用，拌制的砂浆应在3h内使用完毕；当施工期间最高气温超过30℃时，应在2h内使用完毕。预拌砂浆及蒸压加气混凝土砌块专用砂浆的使用时间应按照厂家提供的说明书确定。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]