[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144580,800,1,"单选题","通常在预应力混凝土楼盖中的张拉顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先张拉楼板、后张拉楼面梁",true,{"key":16,"text":17,"correct":18},"B","板中的无粘结筋须集中张拉",false,{"key":20,"text":21,"correct":18},"C","先张拉楼面梁、后张拉楼板",{"key":23,"text":24,"correct":18},"D","板中的无粘结筋须分批张拉","2020教材P113 \u002F 2019教材P112 预应力楼盖宜先张拉楼板、次梁，后张拉主梁的预应力筋；对于平卧重叠构件，宜先上后下逐层张拉。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]