[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144579,800,1,"单选题","后张法无粘结预应力混凝土梁板施工中，预应力筋的张拉顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先张拉梁，后张拉板",false,{"key":16,"text":17,"correct":18},"B","先张拉板，后张拉梁",true,{"key":20,"text":21,"correct":14},"C","梁和板交替张拉",{"key":23,"text":24,"correct":14},"D","根据施工方便确定","2020教材P113 \u002F 2019教材P112 预应力楼盖宜先张拉楼板、次梁，后张拉主梁的预应力筋；对于平卧重 叠构件，宜先上后下逐层张拉。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]