[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144577":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144577,800,2,"多选题","后张法有粘结预应力施工中，与预应力筋孔道同时留设的孔道有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","观测孔",false,{"key":16,"text":17,"correct":14},"B","加压孔",{"key":19,"text":20,"correct":21},"C","灌浆孔",true,{"key":23,"text":24,"correct":21},"D","排气孔",{"key":26,"text":27,"correct":21},"E","泌水管。","CDE","2020教材P113 \u002F 2019教材P112 （五）后张法预应力施工（1） 预应力筋孔道形状有直线、曲线和折线三种类型。孔道的留设可采用预埋金属螺旋管留孔、预埋塑料波纹管留孔、抽拔钢管留孔和胶管充气抽芯留孔等方法。在留设预应力筋孔道的同时，尚应按要求合理留设灌浆孔、排气孔和泌水管。答案选CDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]