[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144568":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144568,800,2,"多选题","关于先张法与后张法相比的不同点的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","张拉机械不同",false,{"key":16,"text":17,"correct":18},"B","张拉控制应力不同",true,{"key":20,"text":21,"correct":18},"C","先张法的锚具可取下来重复使用，后张法则不能",{"key":23,"text":24,"correct":18},"D","施工工艺不同",{"key":26,"text":27,"correct":14},"E","先张法适用于生产大型预应力混凝土构件，后张法适用于生产中小型构件","BCD","2020教材P112 \u002F 2019教材P111 页 先张法特点是：先张拉预应力筋后，再浇筑混凝土；预应力是靠预应力筋与混凝土之间的粘结力传递给混凝土，并使其产生预压应力。 后张法是先淺筑构件或结构混凝土，待达到一定强度后，在构件或结构上张拉预应力筋，然后用锚具将预应力筋固定在构件或结构上的方法。特点是：先浇筑混凝土，达到一定强度后，再在其上张拉预应力筋；预应力是靠锚具传递给混凝土，并使其产生预压应力。 正确选项为BCD",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]