[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144564":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1144564,800,1,"单选题","地上结构后浇带保温养护应至少保持（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7d",false,{"key":16,"text":17,"correct":14},"B","1Od",{"key":19,"text":20,"correct":21},"C","14d",true,{"key":23,"text":24,"correct":14},"D","21d","2020教材P112 \u002F 2019教材P111 后浇带的设置和处理 后浇带是在现浇钢筋混凝土结构施工过程中，为克服由于温度、 收缩等原因导致有害 裂缝而设置的临时施工缝。后浇带通常根据设计要求留设， 并在主体结构保留一段时间（若 设计无要求，则至少保留 28d） 后再饶筑，将结构连成整体。 填充后浇带， 可采用微膨胀混凝土、强度等级比原结构强度提高一级，并保持至少 14d 的湿润养护。后浇带接缝处按施工缝的要求处理。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]