[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144563,800,1,"单选题","为在现浇钢筋混凝土结构施工过程中，克服由于温度、收缩等而可能产生有害裂缝而设置的临时施工缝，称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预留带",false,{"key":16,"text":17,"correct":18},"B","后浇带",true,{"key":20,"text":21,"correct":14},"C","涨缝",{"key":23,"text":24,"correct":14},"D","纵缝","2020教材P112 \u002F 2019教材P111 本题考核的是后浇带的设置。后浇带是在现浇钢筋混凝土结构施工过程中，为克服由于温度、收缩等可能产生有害裂缝而设置的临时施工缝。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]