[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144556":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144556,800,1,"单选题","混凝土浇筑中，在浇筑与柱和墙连成整体的梁和板时，应在柱和墙浇筑完毕后间歇（ ）h再继续浇筑。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.5～1.0",false,{"key":16,"text":17,"correct":18},"B","1.0~1.5",true,{"key":20,"text":21,"correct":14},"C","1.5～2.0",{"key":23,"text":24,"correct":14},"D","2.0～2.5","2020教材P111 \u002F 2019教材P110 在浇筑与柱和墙连成整体的梁和板时，应在柱和墙浇筑完毕后停歇1～1.5h，再继续浇筑。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]