[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144554":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144554,800,2,"多选题","施工缝的位置应在混凝土浇筑之前确定，下列做法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","有主次梁的楼板，施工缝应留置在主梁跨中500mm范围内",false,{"key":16,"text":17,"correct":18},"B","和板连成整体的大截面梁，留置在板底以下20～30mm处",true,{"key":20,"text":21,"correct":18},"C","单向板留置在平行于板的短边的任何位置",{"key":23,"text":24,"correct":18},"D","无梁楼板柱的施工缝宜留置在柱帽的下面",{"key":26,"text":27,"correct":18},"E","墙的留置在门洞口过梁跨中1\u002F3范围内","BCDE","2020教材P111 \u002F 2019教材P110 施工缝的位置应在混凝土浇筑之前确定，并宜留置在结构受× f力较小且便于施工的部位。蹿工缝的留置位置应符合下列规定： 1 ）柱: 宜留置在基础、楼板、梁的顶面，梁和吊车梁牛腿、无梁楼板柱帽的下面； 2 ）与被连成整体的大截面梁（高超过lm），留置在板底面以下20~3 0 m m处，当板 下有梁托时，留置在梁托下部； 3 ）单向板：留置在平行于板的短边的任何位置； 4 ）有主次梁的楼板，施工缝应留置在次梁跨中1\u002F3范围内； 5 ）墙留置在门洞口过梁跨中1\u002F3范围内，也可留在纵横墙的交接处； 6 ）双向受力板、大体积混凝土结构、拱、穹拱、薄壳、蓄水池、斗仓、多层钢架及 其他结构复杂的工程，施工缝的位置应按设计要求留置",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]