[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144528":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1144528,800,1,"单选题","关于基础钢筋施工的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","钢筋网绑扎时，必须将全部钢筋相交点扎牢，不可漏绑",false,{"key":16,"text":17,"correct":14},"B","底板双层钢筋，上层钢筋弯钩朝下，下层可朝上或水平",{"key":19,"text":20,"correct":21},"C","纵向受力钢筋混凝土保护层不应小于40mm，无垫层时不应小于70mm",true,{"key":23,"text":24,"correct":14},"D","独立柱基础为双向钢筋时，其底面长边钢筋应放在短边钢筋的上面","2020教材P108 \u002F 2019教材P107 钢筋网的绑扎。四周两行钢筋交叉点应每点扎牢，中间部分交叉点可相隔交错扎牢，但必须保证受力钢筋不位移。双向主筋的钢筋网，则须将全部钢筋相交点扎牢。绑扎时应注意相邻绑扎点的钢丝扣要绑成八字形，以免网片歪斜变形。钢筋的弯钩应朝上，不要倒向一边；但双层钢筋网的上层钢筋弯钩应朝下。独立柱基础为双向钢筋时，其底面短边的钢筋应放在长边钢筋的上面。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]