[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144525":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1144525,800,1,"单选题","钢筋工程机械连接接头试验时发现有1个试件的抗拉强度不符合要求，这时应再取（ ）个试件进行复检。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","5",{"key":22,"text":23,"correct":24},"D","6",true,"2020教材P107 \u002F 2019教材P106 在施工现场， 应按国家现行标准抽取钢筋机械连接接头、 焊接接头试件作力学性能检验， 其质量应符合有关规程的规定。钢筋接头以3个为一批，复查双倍。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]