[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144481":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144481,800,1,"单选题","关于钢筋工程施工工艺的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钢筋放样→钢筋制作→钢筋半成品运输→基础垫层→弹钢筋定位线→钢筋绑扎→钢筋验收、隐蔽",true,{"key":16,"text":17,"correct":18},"B","钢筋制作→钢筋放样→钢筋半成品运输→基础垫层→弹钢筋定位线→钢筋绑扎→钢筋验收、隐蔽",false,{"key":20,"text":21,"correct":18},"C","钢筋放样→钢筋半成品运输→钢筋制作→基础垫层→弹钢筋定位线→钢筋绑扎→钢筋验收、隐蔽",{"key":23,"text":24,"correct":18},"D","钢筋半成品运输→钢筋放样→钢筋制作→基础垫层→弹钢筋定位线→钢筋绑扎→钢筋验收、隐蔽","2020\u002F2019版教材P99 钢筋工程工艺流程：钢筋放样 -钢筋制作-钢筋半成品运输—基础垫层— 弹钢筋定位线-钢筋绑扎-钢筋验收、隐蔽",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]