[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144469":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144469,800,1,"单选题","钢筋混凝土预制桩采用锤击沉桩法施工时，其施工工序包括：①打桩机就位；②确定桩位和沉桩顺序；③吊桩喂桩；④校正；⑤锤击沉桩。通常的施工顺序为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③④⑤",false,{"key":16,"text":17,"correct":18},"B","②①③④⑤",true,{"key":20,"text":21,"correct":14},"C","①②③⑤④",{"key":23,"text":24,"correct":14},"D","②①③⑤④","2020\u002F2019版教材P95 锤击沉桩法是利用桩锤下落产生的冲击功克服土对桩的阻力，使桩沉到设计深度。施工程序：确定桩位和沉桩顺序→桩机就位→吊桩喂桩→校正→锤击沉桩→接桩→再锤击沉桩→送桩→收锤→切割桩头。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]