[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144468":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144468,800,1,"单选题","关于钢筋混凝土预制桩沉桩顺序的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对于密集桩群，从四周开始向中间施打",false,{"key":16,"text":17,"correct":18},"B","一侧毗邻建筑物时，由毗邻建筑物处向另一方向施打",true,{"key":20,"text":21,"correct":14},"C","对基础标高不一的桩，宜先浅后深",{"key":23,"text":24,"correct":14},"D","对不同规格的桩，宜先小后大、先短后长","2020\u002F2019版教材P95 沉桩顺序应按先深后浅、先大后小、先长后短、 先密后疏的次序进行。对于密集 桩群应控制沉桩速率， 宜从中间向四周或两边对称施打； 当一侧毗邻建筑物时，由毗邻建 筑物处向另一方向施打",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]