[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144467":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144467,800,2,"多选题","关于钢筋混凝土预制桩锤击沉桩顺序的表述，说法正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对于密集桩群，从中间开始分头向四周或两边对称施打",true,{"key":16,"text":17,"correct":14},"B","当一侧毗邻建筑物时，由毗邻建筑物处向另一方向施打",{"key":19,"text":20,"correct":21},"C","对基础标高不一的桩，宜先浅后深",false,{"key":23,"text":24,"correct":14},"D","对不同规格的桩，宜先大后小、先长后短",{"key":26,"text":27,"correct":14},"E","当基坑不大时，打桩可从中间开始分头向两边进行","ABDE","2020\u002F2019版教材P95 5） 沉桩顺序应按先深后浅、先大后小、先长后短、先密后疏的次序进行。对于密集桩群应控制沉桩速率，宜从中间向四周或两边对称施打；当一侧毗邻建筑物时，由毗邻建筑物处向另一方向施打。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]