[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144466":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144466,800,1,"单选题","关于静力压桩法施工的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工前进行试压粧，数量不少于3根。",true,{"key":16,"text":17,"correct":18},"B","采用静压粧的基坑，可边挖桩边开挖基坑",false,{"key":20,"text":21,"correct":18},"C","送桩深度大于4m送桩器应专门设计",{"key":23,"text":24,"correct":18},"D","静压桩应以压力为主，标高为辅","2020\u002F2019版教材P95 施工前进行试压桩，数量不少于 3 根。 采用静压粧的基坑，不应边挖桩边开挖基坑。 送桩深度大于 8m 送桩器应专门设计。 静压桩应以标高为主，压力为辅。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]