[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144463":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144463,800,2,"多选题","关于条形混凝土基础浇筑技术的说法，正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","浇筑前，应根据混凝土基础顶面的标高在两侧木模上弹出标高线",true,{"key":16,"text":17,"correct":14},"B","根据基础深度宜分段分层连续浇筑混凝土，一般不留施工缝",{"key":19,"text":20,"correct":14},"C","各段层间应相互衔接，每段间浇筑长度控制在2～3m距离",{"key":22,"text":23,"correct":14},"D","逐段逐层呈阶梯形向前推进",{"key":25,"text":26,"correct":27},"E","采用原槽土模时，在基槽两侧的土壁上交错打入长50mm左右的标杆，并露出20～30mm",false,"ABCD","2020\u002F2019版教材P100 条形基础浇筑 （1）浇筑前，应根据混凝土基础顶面的标高在两侧木模上弹出标高线；如采用原槽土模时，应在基槽两侧的土壁上交错打入长100mm左右的标杆，并露出20～30mm，标杆面与基础顶面标高平，标杆之间的距离约3m。 （2）根据基础深度宜分段分层连续浇筑混凝土，一般不留施工缝。各段层间应相互衔接，每段间浇筑长度控制在2～3m，做到逐段逐层呈阶梯形向前推进。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]