[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144434":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1144434,800,1,"单选题","设计无要求时，降水工作应持续到（ ）施工完成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","底板",false,{"key":16,"text":17,"correct":18},"B","基础",true,{"key":20,"text":21,"correct":14},"C","装饰装修",{"key":23,"text":24,"correct":14},"D","主体结构","2020\u002F2019版教材P89 在地下水位以下挖土，应在基坑四周挖好临时排水沟和集水井，或采用井点降水，将水位降低至坑底以下500mm以上，以利挖方进行。降水工作应持续到基础（包括地下水位下回填土）施工完成。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]