[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144421":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144421,800,2,"多选题","关于土方开挖的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基坑开挖可采用机械直接开挖至基底标高",false,{"key":16,"text":17,"correct":18},"B","基坑开挖方案应根据支护结构设计、降排水要求确定",true,{"key":20,"text":21,"correct":18},"C","土方开挖前应先进行测量定位，设置好控制点",{"key":23,"text":24,"correct":18},"D","软土基坑必须分层均衡开挖",{"key":26,"text":27,"correct":18},"E","基坑开挖完成后应及时验槽，减少暴露时间","BCDE","2020\u002F2019版教材P88 土方开挖的原则：开槽支撑、先撑后挖、分层开挖、严禁超挖。开挖前先进行测量定位、抄平放线，设置好控制点。挖土要分层进行，分层厚度应根据工程具体情况（包括土质、环境等）决定，开挖本身是一种卸荷过程，防止局部区域挖土过深、卸载过速，引起土体失稳，降低土体抗剪性能。机械开挖至接近设计坑底标高或边坡边界时应预留20～30cm厚的土层，用人工开挖和修坡，边挖边修坡，保证标高符合设计要求。基坑开挖完成后，应及时清底、验槽，减少暴露时间，防止暴晒和雨水浸刷破坏地基土的原状结构。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]