[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144420":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144420,800,1,"单选题","关于土方开挖的顺序、方法的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","开槽支撑，先撑后挖，分层开挖",true,{"key":16,"text":17,"correct":18},"B","支撑开槽，先撑后挖，分层开挖",false,{"key":20,"text":21,"correct":18},"C","开槽支撑，后挖先撑，分层开挖",{"key":23,"text":24,"correct":18},"D","支撑开槽，后挖先撑，分层开挖","2020\u002F2019版教材P88 土方开挖的顺序、 方法必须与设计要求相一致，并遵循“开槽支撑，先撑后挖，分层开挖，严禁超挖” 的原则。严禁在基坑（槽） 及建（构） 筑物周边影响范围内堆放土方。基坑边界周围地面应设排水沟， 对坡顶、坡面、坡脚采取降排水措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]