[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144408":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144408,800,2,"多选题","下列有关基础工程施工的说法中，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工中地下水位应保持在基坑底面以下0.5~1.5m",true,{"key":16,"text":17,"correct":18},"B","对于密集沉桩桩群，应从四周开始往中间施工",false,{"key":20,"text":21,"correct":14},"C","垫层混凝土应在基础验槽后立即浇筑，混凝土强度达到70%后方可进行后续施工",{"key":23,"text":24,"correct":14},"D","验槽时，对于基底以下的土层不可见部位，要先辅以钎探配合共同完成",{"key":26,"text":27,"correct":14},"E","当基础下的持力层较软弱，常采用换土垫层法来处理","ACDE","2020\u002F2019版教材P87 施工中地下水位应保持在基坑底面以下 0.5 ~ 1.5m 验槽方法通常主要采用观察法， 而对于基底以下的土层不可见部位，要先辅以钎探法配合共同完成。 对于密集桩群应控制沉桩速率， 宜从中间向四周或两边对称施打； 当一侧毗邻建筑物时，由毗邻建筑物处向另一方向施打 垫层混凝土应在基础验槽后立即浇筑，混凝土强度达到 70% 后方可进行后续施工。 换填地基适用于浅层软弱土层或不均匀土层的地基处理。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]