[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144405":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1144405,800,1,"单选题","当基坑底为隔水层且层底作用有承压水时，应进行（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基坑边坡加固",false,{"key":16,"text":17,"correct":14},"B","地基处理",{"key":19,"text":20,"correct":21},"C","坑底突涌验算",true,{"key":23,"text":24,"correct":14},"D","边坡失稳验算","2020\u002F2019版教材P87 当基坑底为隔水层且层底作用有承压水时， 应进行坑底突涌验算。必要时可采取水平封底隔渗或钻孔减压措施，保证坑底土层稳定，避免突涌的发生。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]