[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144362":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144362,800,2,"多选题","建筑变形观测过程中，必须立即报告委托方，并及时增加观测次数或调整变形测量方案的情况有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","变形量达到预警值",true,{"key":16,"text":17,"correct":18},"B","暴雨多发季节",false,{"key":20,"text":21,"correct":14},"C","开挖面出现塌陷、滑坡",{"key":23,"text":24,"correct":14},"D","周边建筑沉降出现异常",{"key":26,"text":27,"correct":14},"E","变形量、变形速率出现异常变化","ACDE","2020\u002F2019版教材P79 当建筑变形观测过程中发生下列情况之一时，必须立即报告委托方，同时应及时增加观测次数或调整变形测量方案：（1）变形量或变形速率出现异常变化。（2）变形量达到或超出预警值。（3）周边或开挖面出现塌陷、滑坡。（4）建筑本身、周边建筑及地表出现异常。（5）由于地震、暴雨、冻融等自然灾害引起的其他变形异常情况。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]