[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1144359,800,1,"单选题","高层建筑开始进行变形观测的时点是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基础垫层施工时",false,{"key":16,"text":17,"correct":14},"B","基础施工时",{"key":19,"text":20,"correct":21},"C","基础底板完成后",true,{"key":23,"text":24,"correct":14},"D","地下室砌筑完成后","2020\u002F2019版教材P78 普通建筑可在基础结构完工或地下室砲筑完工后开始进行变形观测；大型、高层建筑可在基础垫层或基础底板完成后开始进行变形观测。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]