[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1144358,800,1,"单选题","关于普通建筑开始沉降观测时间的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基础完工后和地下室砌筑完后",true,{"key":16,"text":17,"correct":18},"B","主体完工或地下室砌筑完后",false,{"key":20,"text":21,"correct":18},"C","基础垫层或基础底部完成后",{"key":23,"text":24,"correct":18},"D","基础垫层完工或地下室砌筑完后","2020\u002F2019版教材P78 沉降观测的周期和时间要求有： 在基础完工后和地下室砌完后开始观测； 民用高层建筑宜以每加高 2 ~ 3 层观测 1 次； 工业建筑宜按回填基坑、安装柱子和屋架、砌筑墙体、设备安装等不同阶段进行观测。如建筑施工均匀增高， 应至少在增加荷载的 25%、 50%、 75%、 100% 时各测 1 次。施工中若暂时停工，停工时及重新开时要各测 1 次，停工期间每隔 2 ~ 3 月测 1 次。竣工后运营阶段的观测次数： 在第一年观测 3 ~ 4 次。第二年观测 2 ~ 3 次。第三年开始每年 1 次，到沉降达到稳定状态和满足观测要求为止",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]