[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144355":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1144355,800,2,"多选题","超高层建筑在施工期间必须进行的变形测量有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","沉降观测",true,{"key":16,"text":17,"correct":14},"B","场地沉降观测",{"key":19,"text":20,"correct":21},"C","结构层间压缩测量",false,{"key":23,"text":24,"correct":14},"D","地基土分层沉降观测",{"key":26,"text":27,"correct":14},"E","倾斜观测","ABDE","2020\u002F2019版教材P77 建筑在施工期间的变形测量要求： 1） 对各类建筑应进行沉降观测，宜进行场地沉降观测、 地基土分层沉降观测和斜坡位移观测。 2 ） 对基坑工程应进行基坑及其支护结构变形观测和周边环境变形观测； 对一级基坑应进行基坑回弹观测。 3） 对高层和超高层建筑，应进行倾斜观测。 4） 当建筑出现裂缝时，应进行裂缝观测。 5） 施工需要时， 进行其他类型的变形观测。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]