[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144343":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1144343,800,1,"单选题","某大中型的商场施工项目平面控制测量的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","平面控制测量必须遵循“由局部到整体”的组织实施原则",false,{"key":16,"text":17,"correct":14},"B","先建立建筑物施工控制网，再建立场区控制网",{"key":19,"text":20,"correct":21},"C","以平面控制网的控制点测设建筑物的主轴线",true,{"key":23,"text":24,"correct":14},"D","根据副轴线进行建筑物的细部放样","2020\u002F2019版教材P75 平面控制测量必须遵循“由整体到局部”的组织实施原则，以避免放样误差的积累。大中型的施工项目，应先建立场区控制网，再分别建立建筑物施工控制网，以建筑物平面控制网的控制点为基础，测设建筑物的主轴线，根据主轴线再进行建筑物的细部放样；规模小或精度高的独立项目或单位工程，可通过市政水准测控控制点直接布设建筑物施工控制网。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]