[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1144338":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1144338,800,1,"单选题","竣工总图实测依据的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","城市坐标水准点",false,{"key":16,"text":17,"correct":14},"B","城市海拔高程点",{"key":19,"text":20,"correct":21},"C","施工控制点",true,{"key":23,"text":24,"correct":14},"D","临近区域控制点","2020\u002F2019版教材P75 竣工总图的实测，应在已有的施工控制点（桩）上进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]