[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143922":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143922,800,2,"多选题","施工过程中， 施工组织设计应进行修改或补充的情形包括（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程设计有重大修改",true,{"key":16,"text":17,"correct":14},"B","有关标准规范修订和废止",{"key":19,"text":20,"correct":21},"C","单位破产重组",false,{"key":23,"text":24,"correct":21},"D","主要施工方法有一般调整",{"key":26,"text":27,"correct":14},"E","施工环境有重大改变","ABE","",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]