[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143886,800,1,"单选题","专项方案实施前， 应由（） 向现场管理人员和作业人员进行安全技术交底。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目专职安全员",false,{"key":16,"text":17,"correct":14},"B","质检员",{"key":19,"text":20,"correct":21},"C","项目技术负责人",true,{"key":23,"text":24,"correct":14},"D","项目负责人","",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]