[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143876":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143876,800,1,"单选题","下列不属于项目成本核算三同步原则的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","形象进度",false,{"key":16,"text":17,"correct":18},"B","纠正偏差",true,{"key":20,"text":21,"correct":14},"C","产值统计",{"key":23,"text":24,"correct":14},"D","成本归集","项目成本核算应坚持形象进度、产值统计、成本归集的三同步原则。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]