[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143874":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143874,800,1,"单选题","关于等节奏流水施工的说法，错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","各施工过程在各个施工段流水节拍相等",false,{"key":16,"text":17,"correct":14},"B","相邻施工过程的流水步距相等",{"key":19,"text":20,"correct":14},"C","专业工作队数等于施工过程数",{"key":22,"text":23,"correct":24},"D","各专业工作队在各施工段上不能连续作业",true,"等节奏流水施工特点： （1）所有施工过程在各个施工段上的流水节拍均相等； （2）相邻施工过程的流水步距相等，且等于流水节拍； （3）专业工作队数等于施工过程数，即每一个施工过程成立一个专业工作队，由该队完成相应施工过程所有施工任务； （4）各个专业工作队在各施工段上能够连续作业，施工段之间没有空闲时间。 考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]