[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143865":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143865,800,2,"多选题","关于吊装工程构件堆放时的要求， 下列说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","构件堆放处，底部按设计位置设置垫木",false,{"key":16,"text":17,"correct":18},"B","构件多层叠放时，梁不超过5层",true,{"key":20,"text":21,"correct":14},"C","钢屋架多层叠放时，各层的支承垫木应在同一垂直线上",{"key":23,"text":24,"correct":18},"D","钢屋架多层叠放时，各堆放构件之间应留不小于0.5m宽的通道",{"key":26,"text":27,"correct":14},"E","重心较高的屋架堆放时，应在两侧加设支撑","BD","吊装工程构件堆放要求： （1）构件堆放平稳，底部按设计位置设置垫木。 （2）构件多层叠放时，柱子不超过2层；梁不超过3层；大型屋面板.多孔板6～8层；钢屋架不超过3层， 各层的支承垫木应在同一垂直线上，各堆放构件之间应留不小于0.7m宽的通道。 （3）重心较高的构件（如屋架、大架等），除在底部设垫木外，还应在两侧加设支撑或将几榀大梁以方木铁丝连成一体，提高其稳定性，侧向支撑沿梁长度方向不得少于3道。墙板堆放架应经设计计算确定，并确保地面抗倾覆要求。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]