[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143863":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143863,800,1,"单选题","施工现场临时用电设备在 5 台及以上或设备总容量达到（ ） kW 及以上者， 应编制用电组织设计。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50",true,{"key":16,"text":17,"correct":18},"B","100",false,{"key":20,"text":21,"correct":18},"C","150",{"key":23,"text":24,"correct":18},"D","200","施工现场临时用电设备在5台及以上或设备总容量在50kW及以上者，应编制用电组织设计。否则应制定安全用电和电气防火措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]