[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143857":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143857,800,1,"单选题","下列流水施工的基本组织形式中，其专业工作队数大于施工过程数的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","等节奏流水施工",false,{"key":16,"text":17,"correct":14},"B","异步距异节奏流水施工",{"key":19,"text":20,"correct":21},"C","等步距异节奏流水施工",true,{"key":23,"text":24,"correct":14},"D","无节奏流水施工","等步距异节奏流水施工特点： （1）同一施工过程在其各个施工段上的流水节拍均相等，不同施工过程的流水节拍不等，其值为倍数关系。 （2）相邻施工过程的流水步距相等，且等于流水节拍的最大公约数； （3）专业工作队数大于施工过程数，部分或全部施工过程按倍数增加相应专业工作队； （4）各个专业工作队在施工段上能够连续作业，施工段间没有间隔时间。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]